3.35.030 Building permits.
Fee/Charge |
Reference |
|
---|---|---|
State: |
||
State Bldg. Code Council – charged on all residential building permits issued. |
$6.50 an additional surcharge of $2.00 for each additional unit |
|
State Bldg. Code Council – charged on all commercial building permits issued. |
$25.00 an additional surcharge of $2.00 for each additional unit |
|
Building: |
||
Building permit based on improvement value. (Construction value is established by using the most current Building Valuation Data sheet, provided by the International Code Council.) |
Permit fee |
|
Value of improvement: |
||
$1.00 to $10,000 (Based on a one-time inspection, additional fees will be assessed for any additional inspections needed.) |
$50.00 |
|
$10,001 to $11,000 |
$195.25 |
|
$11,001 to $12,000 |
$209.25 |
|
$12,001 to $13,000 |
$223.25 |
|
$13,001 to $14,000 |
$237.25 |
|
$14,001 to $15,000 |
$251.25 |
|
$15,001 to $16,000 |
$265.25 |
|
$16,001 to $17,000 |
$279.25 |
|
$17,001 to $18,000 |
$293.25 |
|
$18,001 to $19,000 |
$307.25 |
|
$19,001 to $20,000 |
$321.25 |
|
$20,001 to $21,000 |
$335.25 |
|
$21,001 to $22,000 |
$349.25 |
|
$22,001 to $23,000 |
$363.25 |
|
$23,001 to $24,000 |
$377.25 |
|
$24,001 to $25,000 |
$391.25 |
|
$25,001 to $50,000 |
$391.75 for the first $25,000 + $10.10 for each add’l $1,000, or fraction thereof |
|
$50,001 to $100,000 |
$643.75 for the first $50,000 + $7.00 for each add’l $1,000, or fraction thereof |
|
$100,001 to $500,000 |
$993.75 for the first $100,000 + $5.60 for each add’l $1,000, or fraction thereof |
|
$500,001 to $1,000,000 |
$3,233.75 for the first $500,000 + $4.75 for each add’l $1,000 or fraction thereof |
|
$1,000,001 and up |
$5,608.75 for the first $1,000,000 + $3.65 for each add’l $1,000 or fraction thereof |
|
Plan review |
||
Improvement value less than $10,000 |
No plan review fee |
|
Improvement value greater than $10,000 |
65% of bldg. permit fee (when a plan review is required) |
|
Fast track plan review |
100% of bldg. permit fee |
Admin. Order No. 76 |
Foundation only |
Cost |
|
Plumbing: |
||
Minimum permit fee |
$50.00 |
|
Gas appliance and piping installation permit fee |
$50.00 |
|
Restoration of surface by City and inspection: |
||
Restoration + 1 year of maintenance |
Cost |
|
Testing new piping: |
||
Expense tests and inspections |
Cost |
|
Factory-assembled/mobile homes: |
||
Placement permit |
$50.00 |
|
Moving buildings: |
||
Without use of public R.O.W. |
$25.00 |
|
With use of R.O.W. |
$100.00 |
|
Into City limits from outside City limits |
$100.00 |
|
From within City limits to outside City limits |
$25.00 |
|
Mechanical permit: |
||
Minimum permit fee |
$50.00 |
|
Fire safety inspections: |
||
Initial inspection – All moderate hazard and all high hazard inspections taking less than two hours inspection time. (Moderate hazard is billed in annual increments of $37.50 – high hazard is billed $75.00 annually) |
$75.00 |
|
High hazard inspections of two hours or more duration |
$150.00 |
|
Re-inspection (first re-inspection is w/o fee) |
$75.00 |
|
Signs: |
||
Application fee |
$50.00 |
|
Demolition permits: |
$50.00 |
|
Right-of-way permits: |
$50.00 |
|
Grading/scrubbing only |
$50.00 |
|
Street cut – including inspection of surfaces: |
||
Unpaved surfaces |
$10.00 |
[Ord. 4515 § 1, 2021; Ord. 4313, 2016; Ord. 4168, 2014; Ord. 3964, 2010; Ord. 3859, 2008; Ord. 3543, 2002; Code 1970 § 3.07.030.]